Implementation Unit Industrial Sector Quartell the Foia (Valencia)

Surface 450.000 m2 performance.
Year 2004-2007. PEM 23 M€.
The role of prime contractor for the work execution.
The work performed were:

  • Urbanization of roads and pavements.
  • Sewage networking.
  • Potable drinking water network of 800 m3 buffer tank.
  • Network of low and medium voltage transformer stations.
  • Channeling of municipal network of ditches.
  • Channel rainwater runoff.
  • Paving of roads and parking areas.
  • Landscaping of green areas.
  • Ecological barrier separation CN-340.